The Problem

The ATC (Alstom, TSO and Costain) Joint Venture is the largest of the Crossrail contracts and is delivering the fit-out across the entire tunnelled section of the route. A project of this magnitude requires constant design review and collaboration between Engineering and Design teams.


Solution with
basestone

BaseStone allowed users to digitally redline drawings directly from the field, sync data to the cloud and generate outputs in one click.

The Result

An independent six-month study into the use of BaseStone on this project demonstrated significant productivity gains for the engineering design review and construction as-built redlining processes.

 

Features

  • Seamless data import
  • Offline use
  • Digital redlining
  • Visibility of issues
  • Multiple use cases

Download and share

The case study of our latest release

Design Review

  • Process: Design & Construction Redlining
  • Productivity Gain: 55-95%
  • ATC (Alstom, TSO, Costain) Joint Venture