Client: ATC (Alstom-TSO-Costain) Joint Venture on Crossrail
The Problem
As part of the handover process, engineering teams are responsible for creating as-built redlines. This involves marking up drawings to reflect the as-built.
Solution with basestone
With BaseStone, drawings are redlined directly from the field. A snapshot as-built redline is generated automatically.
The Result
480hrs productivity gain in producing 600 as-built redlines.
Tangible Benefits
It is indicated that using the BaseStone enabled process produced a productivity gain of 480 hours in total for the 600 as-builts created by ATC over 12 months.
This corresponds to a monetary value of £19,200.
Intangible Benefits
Reduced admin burden
Engineers are able to spend the additional time managing engineering issues on the project, helping to ensure that the project as a whole is not held up.
Other benefits include reduced printing and paper costs which were not accounted for in this study but provide an additional saving and environmental benefit.
Download and share
The case study of
our latest release
As-Built Redline Generation
Process: As-Built Redline Generation
User: Engineer
Client: ATC (Alstom-TSO-Costain) Joint Venture on Crossrail